RM 620 widening will affect these familiar local properties
The planned RM 620 improvements at Anderson Mill Road and El Salido Parkway will change both the roadway and the businesses along it.
I reviewed the project information and 2025 public tax rolls to identify affected properties within WTCMUD1. The seven locations I identified have a combined assessed value of $22,529,215.
| Property or business | 2025 assessed value |
|---|---|
| Lord’s Church of Austin | $7,137,014 |
| Walgreens — real estate and business personal property | $4,287,041 |
| AutoZone | $3,306,687 |
| VCA Lakeline Animal Hospital | $2,530,620 |
| Shell/Circle K | $2,349,532 |
| Christian Brothers Automotive | $1,863,954 |
| Mr. Sharky’s Car Wash | $1,054,367 |
| Total | $22,529,215 |
The dollar amounts are assessed values from the tax rolls, not projected tax losses or acquisition payments. The actual tax impact depends on how much of each property is acquired, applicable exemptions, and whether businesses relocate within the District.
See the project maps
-
Detailed roadway map — TxDOT’s May 2023 project schematic. Zoom in to follow the proposed road layout along the corridor.
-
Project overview boards — Illustrated displays from the public hearing.
-
February 2026 final assessment and maps — See Appendix C for roadway schematics and Appendix F, Figures F-1 through F-3, for maps showing the project footprint and potential business displacements.
The overall project affects 25 businesses
TxDOT’s February 2026 Final Environmental Assessment identifies 25 business displacements and approximately 32 acres of additional right-of-way across the full project area. It identifies no residential displacements.
The seven locations above are the properties I identified within WTCMUD1, not the complete list of 25 businesses along the project. Final assessment, Section 5.1
What the road project includes
The project runs approximately 1.2 miles along RM 620, from just south of Foundation Road to Little Elm Trail.
The central change is an elevated bypass with one lane in each direction through the Anderson Mill and El Salido intersections. Through traffic will be able to pass over the traffic signals, while ground-level lanes serve the intersections and nearby properties.
The plans also include:
-
Turnarounds and additional turn lanes.
-
Changes to driveways and business access.
-
A median separating opposing traffic.
-
Walking and bicycling paths, generally 10 feet wide where space allows.
TxDOT project overview · Path and roadway details
Getting to businesses will change
The divided roadway will change some familiar driving routes. At some properties, drivers will need to turn with traffic and use a turnaround or intersection to head in the opposite direction.
TxDOT estimates about two additional minutes for some of these access trips. The project’s intended benefit is faster overall travel through the corridor by allowing through traffic to bypass the two signals. Final Environmental Assessment, Section 5.6.1
The construction timeline
Environmental review was completed in February 2026. The August 2025 wildlife review included in the final assessment lists a proposed mid- to late-2029 construction start, with approximately two years of construction. That is the planning schedule in the reviewed documents; a more recent construction date has not been confirmed. Environmental review status · Final assessment and supporting documents